Once you've confirmed your Chicago property qualifies for a coach house or basement conversion, the next question is the one that decides your whole schedule: how long until you actually have a permit in hand? If you're still working out whether your lot is even eligible, start with our Chicago citywide ADU ordinance guide, which covers the ward opt-in map and who qualifies. This piece picks up where that one ends, at the permit counter.

The short version: Chicago runs a two-stage approval process, and recent city permit records put the building-permit review alone at a median of about 120 days. Plan for roughly four to six months from application to an approved permit, then another four to ten months of construction. Here's how each stage actually works and where the time goes.

Stage One: Pre-Certification with the Department of Housing

Before you can pull a building permit, your project has to clear a separate approval unique to the ADU program. The city's Additional Dwelling Units online portal launched alongside the ordinance on April 1, 2026, and it's where every project begins.

Pre-certification is the city confirming two things: that your property is eligible, and that your proposed unit fits the program's rules. The portal gives immediate feedback as you work through it, including instructions specific to your address. In practice, the step breaks down like this:

  1. Check eligibility. Look up your parcel on the city's official ADU eligibility map, confirm your ward has opted in, and confirm which unit types your zoning allows (conversion, coach house, or both). Do not pay for design work until this clears.
  2. Submit the application. Provide general project and property details and upload required documentation. Expect a neighbor notification affidavit, plus additional affordability documentation if you're proposing two or more units.
  3. Wait for DOH review. Department of Housing staff confirm eligibility and tell you the next steps.

This is the stage homeowners underestimate, because it has no analog in a straightforward remodel. It's also the cheapest insurance you can buy against the most expensive mistake in the process, which is paying an architect to draw plans for a lot that turns out not to qualify.

Stage Two: The Building Permit from the Department of Buildings

Once you're pre-certified, you apply for a building permit with the Department of Buildings (DOB), the same agency that permits any construction in the city. This is where your plans get scrutinized against Chicago's building code and zoning.

For a new coach house, you'll need permit drawings stamped by a licensed architect, because new detached construction in Illinois generally requires it. A basement or attic conversion is usually simpler to document, which is one reason conversions outnumbered coach houses by more than two to one during the city's pilot. The ordinance also caps coach house height at 22 feet to the highest point, so your drawings need to reflect that limit before DOB will sign off.

After pre-certification and a DOB permit, ADUs are permitted by right, meaning there's no discretionary hearing or zoning variance to chase once you're in the program. That's a meaningful advantage over the special-use gauntlet many cities still run.

What the Timeline Actually Looks Like

City permit data gives a clearer picture than any rule of thumb. An analysis of Chicago permit records found the 2024 average from application to permit was 121.6 days across 249 permits, and January through September 2026 Standard Plan Review permits were issued a median of 120 days after application, with the middle half of projects landing between 78 and 183 days. In other words, four months is a realistic floor and six months is common.

Add the pre-certification time in front of that, plus design, and the front half of a Chicago ADU project, from first application to an approved building permit, routinely runs four to six months. Construction then adds another four to ten months depending on unit type and site conditions. A conversion inside existing space moves fastest; a detached coach house with new utility trenching takes longest. Front to back, most projects run close to a year, which is why starting early protects both your timeline and your budget.

Demand is why the queue matters. By mid-March 2026, before the ordinance had even taken effect, the Department of Housing had already pre-certified 816 additional dwelling units, with early activity concentrated on the North and Northwest sides. If your ward has opted in, you are not early anymore, and both the review queue and the small pool of qualified builders book up.

Budget for the Fees, Not Just the Build

The permits themselves carry real cost on the coach house side. In 2026 permit records, Department of Buildings permits for coach houses ran roughly $2,525 to $3,050, plus a $522 open-space impact fee. Those are city fees on top of architect drawings and any ward-specific conditions, and they're separate from the construction price. For the full picture of what a unit costs to build, our Chicago coach house cost breakdown walks through the ranges by unit type, and the how to budget for an ADU guide covers the line items that most often surprise first-time builders.

Where Projects Lose Time (and How to Avoid It)

Most delay isn't the city being slow. It's avoidable friction on the applicant's side:

Find a Chicago ADU Builder Who Knows the Process

The rules aren't the hard part in Chicago anymore. The hard part is finding a builder who has actually shepherded a coach house or conversion through pre-certification and DOB review, meets the apprenticeship requirement, and knows the ward-by-ward opt-in map well enough to keep your project out of the correction queue.

We're building a verified directory of Chicago ADU and coach house builders at adubuilderschicago.com. Check your eligibility first, then head there to connect with builders already working under the 2026 ordinance.


Sources: City of Chicago Additional Dwelling Units Ordinance program and ADU Process page, City of Chicago ADU expansion launch announcement, and Chicago ADU permit-record analysis (permit-lookup/lifeofabit). Timelines are medians from past permit data, not guarantees; fees and review times change. Always confirm your property's eligibility and current requirements on the city's official ADU portal before planning a project.